ITS is updating the VAST storage service’s hardware and software to meet MiStorage customer needs. This update will require a planned outage of the MiServer service.
To minimize impacts to MiServer users, the project may define and implement a streamlined failover process to move data from NCDC to ASB during the outage. If developed and tested, this improved process can then be used in the event of a future unplanned outage at NCDC.
Project Team
- Project Sponsor: Andrew Palms
- Project Owner: Eric Boyd
- Project Manager: Greg Stathes
Major Goals
- Install and configure already purchased upgraded switch hardware equipment at NCDC
- If needed, develop and implement needed associated scripts to facilitate failover and streamline existing failover processes to take advantage of new hardware and scripts
- Deploy outside of normal business hours to minimize impacts to users
Timeline
- Purchase and Install Needed Equipment: 10/25/24
- Complete and Test Scripts: 11/8/24
- Deployment: 1/18 - 1/19