Connecting Michigan Implementation Timeline

License Tasks

  • July 2021: Full Salesforce license users moved to platform licenses

Data/Architecture Tasks

  • May 2021: Met with ITS Unit Reps to define existing processes
  • August 2021: Defined unit business requirements
  • December 2021:

    • Deployed CRM in QA
    • Completed user testing and governance documentation
  • February 2022:

    • Deployed CRM in production
    • Trained end users in CRM

Wrap Up Tasks

  • March 2022:
    • Define Phase 2 Project
    • CRM moves into operations